On the Lumos WMS website, open Inbound → Inbound Receiving or Inbound Consolidation.
- The Receiving line still allows Consolidate.
- Identify the target Loading unit that will receive the goods.
- Check product compatibility and container capacity.
Select goods to consolidate
Open Inbound Receiving
From the Lumos menu, open Inbound Receiving. Find the record and select its row at 1.1 to open the details below the list.
Inbound Receiving page overview - 1.1 = RCV-202610-0001
Open Consolidate
Open the Receiving details, select the ⋯ button on the goods line, and choose Consolidate at 2.1 in the dropdown of an eligible line.
Consolidate in the Receiving line action menu - 2.1 = Consolidate
Enter the quantity and choose the Consolidation dock
Choosing Consolidate opens the Consolidate into existing LU dialog while you remain on Inbound Receiving. Set the quantity and dock in this dialog before choosing the target LU.
- Check the quantity field at the top; its label includes the item’s unit after Planned. Enter a quantity greater than 0 and no higher than the maximum shown in brackets. This example uses 120 bottles.
- Select the Consolidation dock field to open its dropdown, then choose where the AGV should bring the LU, such as PICK-01 in the image. The dropdown closes and the field displays the selected dock.
- If a default dock is already selected, check that it matches your work area. When the warehouse has only one dock, it is selected automatically and the field cannot be changed. The field is hidden when there are no dock options.
Initial form: Planned quantity and Consolidation dock Completed example: Planned quantity and Consolidation dock Select a Target loading unit row and request the fetch
In the same dialog, look under Target loading unit. Each row is directly selectable; there is no additional dropdown or dialog. The first image has no LU selected, so Request fetch is disabled. You must select a row even when only one LU is listed.
- Check each LU code, Bin, On-hand quantity, and Remaining capacity. Select the required LU row, such as LU-000001 at 4.1. Its background changes colour when selected, as shown in the example.
- Check the planned quantity, dock, and selected LU. Request fetch at 4.2 becomes available once a LU is selected, the quantity is valid, and a dock is specified when the field is shown. Select this button to submit the fetch request.
- After a successful request, the dialog closes and a success message appears. Follow the record on Inbound Consolidation as described in the next section. Wait for the LU to arrive at the dock and physically add the goods before selecting Confirm at dock.
Initial form: Target LU selection and fetch request Completed example: Target LU selection and fetch request - 4.1 = LU-000001 selected as the Target loading unit
- 4.2 = Request fetch
After creating the consolidation, go to Inbound Consolidation to follow the LU and its transport tasks.
Follow and confirm at the dock
Open Inbound Consolidation
From the Lumos menu, open Inbound Consolidation. Find the record and select its row at 5.1 to open the details below the list.
Inbound Consolidation page overview - 5.1 = LU-000001
Follow the consolidation Transport Orders
Check the tasks that bring the LU to the Consolidation dock and return it to storage. Operators must move and combine the actual goods as instructed.
Consolidation transport tasks Open Confirm at dock
After physically adding the goods to the Target LU, return to Inbound Consolidation and select that task’s row to open its details below the table. Check the Target LU code, scroll down within the detail panel, and select Confirm at dock at 7.1 to open the quantity confirmation dialog.
Inbound Consolidation page and Confirm at dock in the detail panel - 7.1 = Confirm at dock
Confirm quantity at dock
Check the quantities and Batch No in the confirmation dialog. Select Confirm, then follow the task that returns the LU to storage.
Consolidation confirmation dialog
Check the result
The goods are tracked on the target Loading unit, and receiving progresses with the remaining put-away work.